Van Gogh: we bought a former funeral home

I have to confess: when we bought the building we now call Van Gogh, the ground floor had been a funeral home. Nobody in the team asked too many questions. The visitors, months later, kept telling us they felt good inside. We did not ask why either.

Our projects are named after painters so we never have to say the street. This one is a full building in Ajuda, Lisbon: a ground floor and two floors above it. Here is the case, with the numbers and with the parts that did not go to plan.

The numbers

  • Purchase: €320,000
  • Total investment, works included: €471,000
  • Sales: €622,000 (ground floor €187,000, first floor €215,000, second floor €220,000)
  • Gross profit: €142,000
  • Gross ROI: 30.2%

The building went on the market at the end of August 2025. In two months it had 55 visits and 18 offers, and every unit sold to buyers paying in full, with no mortgage.

What went wrong

  1. The structure asked for more. Beams and slabs needed reinforcement nobody had priced. That added about 15% to the works budget. Priscila, who runs our sites, says she dreams every night of beams falling on her head. This building is where that sentence was born.
  1. Carpentry and window frames arrived about three weeks late. Three weeks in a building site is not a delay. It is interest, insurance and patience, all invoiced together.
  1. Turning the ground floor from a shop into a home was slow and expensive to license. The law is one. The interpretations are many.
  1. The neighbours. During the works there were 16 complaints to the police about noise and access. One morning at 7:30 there were ten people photographing the site. The day before it had been the City Council, the day before that the police. That morning the visitors were three peacocks from the botanical garden next door. If a stone falls on a peacock, the site is shut down.

What we changed

Every project now carries a 20% to 25% structural margin, before anyone draws a sofa. We talk to the neighbours before the first hammer blow, not after the first complaint. We add four to six weeks to every licensing estimate. And suppliers sign delivery dates with consequences attached.

The lesson

A project can go over budget, run late, collect police complaints and peacocks, and still be a good deal. But only if the numbers were built to survive the bad scenario from day one. Van Gogh did. Not because we were lucky, but because the margin was there before the problems were.


Past results do not guarantee future results. This article is not investment advice.